Delays in Building Construction Projects in Ghana
Open accessThe DOI matches its Crossref record; 17 of the 17 references it cites were found in a registry or an index.
Abstract
This study investigates the causes of delay of building construction projects in Ghana to determine the most important according to the key project participants; clients, consultants, and contractors. Thirty-two possible causes of delay were identified from the literature and semi-structured interviews of 15 key players in the implementation process. These delay factors were further categorised into nine major groups. The list of delay causes was subjected to a questionnaire survey for the identification of the most important causes of delay. The field survey included 130 respondents made up of 39 contractors, 37 clients and 54 consultants. The relative importance of the individual causes and the groups were calculated and ranked by their relative importance index. The overall results of the study indicate that the respondents generally agree that financial group factors ranked highest among the major factors causing delay in construction projects in Ghana. The financial group factors were delay in honouring payment certificates, difficulty in accessing credit and fluctuation in prices. Materials group factors are second followed by scheduling and controlling factors.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
(1969) · Elsevier eBooks · doi:10.1016/c2013-0-02211-6 · Cited by 1,670
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422 · cited 4×
“Sweis et al. (2008) studied the causes of delay in residential projects in Jordan and concluded that financial difficulties faced by the contractor and too many change orders by the owner are the leading causes of construction delay.”
BackgroundInfluentialInvestigating Communication: An Introduction to Research Methods
Frey, L. R., Botan, C. H., & Kreps, G. L. (1999) · Cited by 939
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796 · cited 1×
“The high temperatures and high humidity ranging from 25 to 80% certainly affect the productivity of construction workers as a result of dullness of their senses, poor coordination and discomfort from body heat (Frimpong, Oluwoye, and Crawford, 2003).”
BackgroundHill, M., & Stacey, M. (1970) · Population Studies · doi:10.2307/2173066 · Cited by 719
Construction delay: a quantitative analysis
Al-Momani, A. H. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00060-x · Cited by 553 · cited 1×
“Ayman (2000) investigated the causes of delays on 130 public projects in Jordan.”
BackgroundSignificant factors causing delay in the UAE construction industry
Faridi, A. S., & El‐Sayegh, S. M. (2006) · Construction Management and Economics · doi:10.1080/01446190600827033 · Cited by 551
Causes of Delay in Large Building Construction Projects
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:2(45 · Cited by 544 · cited 5×
“Financial difficulties have also been identified as the first major factor causing delay in construction projects in Malaysia (Alaghbari et al. 2007, Assaf et al. 1995).”
BackgroundMethodInfluentialDelays in construction projects: The case of Jordan
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.009 · Cited by 534 · cited 1×
“Sweis et al. (2008) studied the causes of delay in residential projects in Jordan and concluded that financial difficulties faced by the contractor and too many change orders by the owner are the leading causes of construction delay.”
BackgroundProductivity improvement in construction
Oglesby, C. H., Parker, H. W., & Howell, G. A. (1988) · Medical Entomology and Zoology · Cited by 510
The significant factors causing delay of building construction projects in Malaysia
Alaghbari, W., Razali A. Kadir, M., Salim, A., & Ernawati (2007) · Engineering, Construction and Architectural Management · doi:10.1108/09699980710731308 · Cited by 489 · cited 4×
“Fugar, F D K and Agyakwah‐Baah, A B (2010) ‘Delays in building construction projects in Ghana’, Australasian Journal of Construction Economics and Building, 10 (1/2) 103‐116 Sambasvian and Soon (2007) identified the delay factors and their impact on project completion in the Malaysian construction industry.”
BackgroundInfluentialCauses of Delay in Building Construction Projects in Egypt
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2008)134:11(831 · Cited by 463 · cited 2×
“Abd El-Razek et al. (2008) in a similar study in Egypt found that the most important causes of delay are financing by contractor during construction, delays in contractor’s payment by owner, design changes by owner or his agent during construction, partial payments during construction, and…”
BackgroundConstruction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390 · cited 2×
“However, in developing economies Ogunlana et al. (1996) have reported that there are distinctive problems that cause delays in construction.”
BackgroundDelays in Building Construction Projects in Ghana
Fugar, F. D., & Agyakwah-Baah, A. B. (2010) · Australasian Journal of Construction Economics and Building · doi:10.5130/ajceb.v10i1/2.1592 · Cited by 203
Self-citationThe impact of non‐financial incentives on bricklayers' productivity in Nigeria
Fagbenle, O. I., Adeyemi, A. Y., & Adesanya, D. A. (2004) · Construction Management and Economics · doi:10.1080/0144619042000241262 · Cited by 50 · cited 2×
“The relative importance index (RII) was calculated using the following formula (Fagbenle et al., 2004): RII = ∑PiUi ………………………… (1) N (n) Where, RII = relative importance index Pi = respondent’s rating of cause of delay Ui = number of respondents placing identical weighting/rating on cause of…”
Method
Cited by
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Machine learning algorithms for construction projects delay risk prediction
Gondia, A., Siam, A., El-Dakhakhni, W., & Nassar, A. H. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001736 · Cited by 327
Ranking of delay factors in construction projects after Egyptian revolution
Aziz, R. F. (2013) · Alexandria Engineering Journal · doi:10.1016/j.aej.2013.03.002 · Cited by 209
Causes of delay in residential construction projects in Cambodia
Durdyev, S., Omarov, M., & Ismail, S. (2017) · Cogent Engineering · doi:10.1080/23311916.2017.1291117 · Cited by 158
“This outcome substantiates the findings of Fugar and Agyakwah-Baah (2010), who ranked the aforementioned factors as one of the most influencing causes of construction project delay in Ghana.”
ResultConstruction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Metadata
- Authors
- Fugar, F. D., & Agyakwah-Baah, A. B.
- Venue
- Construction Economics and Building
- Published
- 1970-01-01
- Volume
- 10
- Issue
- 1-2
- Pages
- 103-116
- ISSN
- 2204-9029 (ISSN-L)
- OpenAlex
- W2148296242
- Cited by
- 211
- References
- 17
- FWCI
- 0.00
- Type
- journal article
- Language
- en
- Open access
- diamond
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.