Cost overrun in the Malaysian construction industry projects: A deeper insight
The DOI matches its Crossref record; 41 of the 41 references it cites were found in a registry or an index.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
The Good Research Guide: For Small-Scale Social Research Projects
Denscombe, M. (1998) · Cited by 4,557
Design and analysis of pilot studies: recommendations for good practice
Lancaster, G. A., Dodd, S., & Williamson, P. R. (2004) · Journal of Evaluation in Clinical Practice · doi:10.1111/j..2002.384.doc.x · Cited by 2,572
The good research guide for small-scale social research projects.
Kane, M. (1999) · Family Practice · doi:10.1093/fampra/16.2.207-a · Cited by 1,731
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
The concept of project complexity—a review
Baccarini, D. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00093-3 · Cited by 1,192 · cited 1×
“Such tendency has been attributed to increased complexity of refurbishment projects when compared to new build (Baccarini, 1996; Murray, 2000).”
BackgroundUnderestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796 · cited 1×
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundHow common and how large are cost overruns in transport infrastructure projects?
Flyvbjerg, B., Skamris holm, M. K., & Buhl, S. L. (2003) · Transport Reviews · doi:10.1080/01441640309904 · Cited by 783 · cited 1×
“Approximately 45% of projects were completed at or below contract sum; the remainder overran — supporting extant literature stating that negative variance is more common than positive variance (Flyvbjerg et al., 2003; Morris and Hough, 1987; Skamris and Flyvbjerg, 1997).”
BackgroundAnalysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745 · cited 2×
“Several scholars (Doloi et al., 2012; Enshassi et al., 2009; Memon et al., 2013) have identified with the need for greater insight into cost estimation (contract sum) and overrun in construction projects.”
BackgroundFactors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698 · cited 1×
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundSelf-citationAnalysis of factors influencing project cost estimating practice
Akintoye, A. (2000) · Construction Management and Economics · doi:10.1080/014461900370979 · Cited by 608 · cited 1×
“The latter situation typically translates to financial losses for the contractor and/or client (depending on who assumes the burden according to contract terms) (Akintoye, 2000; DeMarco, 2005).”
BackgroundSelf-citationThe effects of construction delays on project delivery in Nigerian construction industry
Aibinu, A. A., & Jagboro, G. O. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00028-5 · Cited by 597 · cited 1×
“Aibinu and Jagboro (2002) suggested an allowance of 17% of total cost”
BackgroundLe-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-008-0367-7 · Cited by 560
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Delays and cost increases in the construction of private residential projects in Kuwait
Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005) · Construction Management and Economics · doi:10.1080/0144619042000326710 · Cited by 456 · cited 1×
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundWhat Causes Cost Overrun in Transport Infrastructure Projects?
FLYVBJERG, B., SKAMRIS HOLM, M. K., & BUHL, S. L. (2004) · Transport Reviews · doi:10.1080/0144164032000080494a · Cited by 455 · cited 2×
“This supports Langdon and Seah (1997) who established that the Malaysian construction industry executed many more small projects than larger ones; but contradicts that literature which suggests that larger projects have the higher cost overruns (Flyvbjerg et al., 2004; Morris and Hough, 1987).”
BackgroundCost overruns in road construction—what are their sizes and determinants?
Odeck, J. (2004) · Transport Policy · doi:10.1016/s0967-070x(03)00017-9 · Cited by 385
Doloi, H. (2013) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000621 · Cited by 325 · cited 1×
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundMorris, P. W. G., & Hough, G. (1987) · UCL Discovery (University College London) · Cited by 300
Delays and cost overruns in the construction projects in the Gaza Strip
Enshassi, A., Al‐Najjar, J., & Kumaraswamy, M. (2009) · Journal of Financial Management of Property and Construction · doi:10.1108/13664380910977592 · Cited by 278 · cited 5×
“Several scholars (Doloi et al., 2012; Enshassi et al., 2009; Memon et al., 2013) have identified with the need for greater insight into cost estimation (contract sum) and overrun in construction projects.”
BackgroundInfluentialCompressing construction durations: lessons learned from Hong Kong building projects
W.M. Chan, D., & M. Kumaraswamy, M. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00032-6 · Cited by 209 · cited 3×
“According to Cleveland (1995), an accurate project cost estimate can provide a good basis for project control during construction; while inaccurate cost estimation is detrimental to both contractors and clients.”
BackgroundMethodInfluentialReasons for delays in public projects in Turkey
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · Construction Management and Economics · doi:10.1080/01446198500000013 · Cited by 198 · cited 1×
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundPreliminary Study on Causative Factors Leading to Construction Cost Overrun
Memon, A. H., Rahman, I. B. A., & Azis, A. A. A. (2011) · International Journal of Sustainable Construction Engineering Technology · Cited by 194
Root-Cause Analysis of Construction-Cost Overruns
Rosenfeld, Y. (2014) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000789 · Cited by 187
Predictors of Cost‐Overrun Rates
Jahren, C. T., & Ashe, A. M. (1990) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1990)116:3(548 · Cited by 134 · cited 1×
“According to some scholars (Flyvbjerg et al., 2004; Jahren and Ashe, 1990), project size is an influence on cost overruns of infrastructure projects because other things being equal, implementation phases can be longer for larger projects, which may induce overruns.”
BackgroundThe importance of the early phase: the case of construction and building projects
Kolltveit, B. J., & Grønhaug, K. (2004) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.03.002 · Cited by 129 · cited 1×
“This supports Langdon and Seah (1997) who established that the Malaysian construction industry executed many more small projects than larger ones; but contradicts that literature which suggests that larger projects have the higher cost overruns (Flyvbjerg et al.”
ResultThree-Stage Least-Squares Analysis of Time and Cost Overruns in Construction Contracts
Bhargava, A., Anastasopoulos, P. C., Labi, S., Sinha, K. C., & Mannering, F. (2010) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000225 · Cited by 118 · cited 1×
“The problem of construction projects exceeding contract sum exists among both developed and developing countries (Anastasopoulos et al., 2010; Sambasivan and Soon, 2007).”
BackgroundReasons for overrun in public sector construction projects in Nigeria
Dlakwa, M. M., & Culpin, M. F. (1990) · International Journal of Project Management · doi:10.1016/0263-7863(90)90032-7 · Cited by 109 · cited 1×
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundEstimating project and activity duration: a risk management approach using network analysis
Dawood, N. N. (1998) · Construction Management and Economics · doi:10.1080/014461998372574 · Cited by 102 · cited 1×
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundAnalysis of non-excusable delay factors influencing contractors' performance in Lagos State, Nigeria
Ibironke, O. T., Oladinrin, O. T., Adeniyi, O., & Eboreime, I. V. (2013) · Journal of Construction in Developing Countries · Cited by 97
Park, Y., & Papadopoulou, T. C. (2012) · Built Environment Project and Asset Management · doi:10.1108/20441241211280873 · Cited by 91
THE PERFORMANCE AND IMPACT OF RAIL MASS TRANSIT IN DEVELOPING COUNTRIES
Fouracre, P. R., Allport, R. J., & Thomson, J. M. (1990) · Publication of: Transport and Road Research Laboratory · Cited by 71
Cost–time performance of public sector housing projects in Nigeria
Okuwoga, A. A. (1998) · Habitat International · doi:10.1016/s0197-3975(98)00014-9 · Cited by 45
Identifying the critical success factors for target cost contracts in the construction industry
Chan, D. W. M., Chan, A. P. C., Lam, P. T. I., & Wong, J. M. W. (2010) · Journal of Facilities Management · doi:10.1108/14725961011058820 · Cited by 40
Time, Cost, and Quality in a Road Building Project
Mateo, J. R. S. C. (2009) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000094 · Cited by 37
Becker, T. C., Jaselskis, E. J., & El-Gafy, M. A. (2014) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000845 · Cited by 28 · cited 3×
“Project costs are commonly categorised as either direct or indirect for contracting, accounting, taxation and other purposes (Becker et al., 2014). However, according to Holland andHobson (1999) there is no universally-accepted categorization framework for the construction industry, to partition construction costs int…”
BackgroundMemon, A. H., Rahman, I. B. A., Azis, A. A. A., & Abdullah, N. H. (2013) · Cited by 25
Cost Performance in Construction Industry of Pakistan
Nawaz, T., Shareef, N. A., & Ikram, A. A. (2013) · Industrial engineering letters · Cited by 19
Lee, H. (2009) · Journal of pharmacopuncture · doi:10.3831/kpi.2009.12.3.103 · Cited by 10
Hajarat, D. A., & Smith, N. J. (1993) · International Journal of Project Management · doi:10.1016/0263-7863(93)90039-p · Cited by 5 · cited 1×
“This is because cost is arguably one of the most fundamental criteria for measuring the success of any project (Becker et al., 2014; Hajarat and Smith, 1993; Memon et al., 2013; San Cristóbal, 2009).”
BackgroundSpon's Asia Pacific Construction Costs Handbook
SEAH, L. (2015) · CRC Press eBooks · doi:10.1201/b18452 · Cited by 4
Cited by
Effect of lean tools to control external environment risks of construction projects
Ansah, R. H., & Sorooshian, S. (2017) · Sustainable Cities and Society · doi:10.1016/j.scs.2017.03.027 · Cited by 92
Metadata
- Authors
- Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2014-11
- Volume
- 32
- Issue
- 8
- Pages
- 1471-1480
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2016324626
- Cited by
- 210
- References
- 41
- FWCI
- 13.96
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.