Causes of Delay in Large Building Construction Projects
The DOI matches its Crossref record; 2 of the 2 references it cites were found in a registry or an index.
Abstract
The present paper outlines the main causes of delay in large building projects in Saudi Arabia and their relative importance. A survey of a randomly selected sample of 24 contractors, 15 architectural/engineering firms (A/E), and nine owners from the Eastern Province of Saudi Arabia was undertaken. The survey included 56 causes of delay, and the respondents were asked to indicate their degree of importance. The delay factors were grouped into nine major groups. The level of importance of the causes and the groups were measured and ranked by their importance index for contractors, owners and A/Es. It was found that contractors, A/Es, and owners generally agree on the ranking of the individual delay factors. It was also shown that contractors and A/Es substantially agree on the ranking of the groups of delay factors, whereas contractors and owners, and A/Es and owners do not agree. It was also shown that the financing group of delay factors was ranked the highest by all three parties and that environment was ranked the lowest.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Statistics for Management and Economics.
Lowther, J., Keller, G., & Warwick, B. (1997) · The Journal of the Operational Research Society · doi:10.2307/3010500 · Cited by 800
Causes of Delay in the Construction Industry
Baldwin, J. R., Manthei, J. M., Rothbart, H. A., & Harris, R. B. (1971) · Journal of the Construction Division · doi:10.1061/jcceaz.0000305 · Cited by 118
Cited by
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Self-citationCauses and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Analysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745
Criteria of project success: an exploratory re-examination
Lim, C. S., & Mohamed, M. Z. (1999) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00040-4 · Cited by 731
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
Cost escalation and schedule delays in road construction projects in Zambia
Kaliba, C., Muya, M., & Mumba, K. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.07.003 · Cited by 596
Construction delay: a quantitative analysis
Al-Momani, A. H. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00060-x · Cited by 553
Significant factors causing delay in the UAE construction industry
Faridi, A. S., & El‐Sayegh, S. M. (2006) · Construction Management and Economics · doi:10.1080/01446190600827033 · Cited by 551
Delays in construction projects: The case of Jordan
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.009 · Cited by 534
The significant factors causing delay of building construction projects in Malaysia
Alaghbari, W., Razali A. Kadir, M., Salim, A., & Ernawati (2007) · Engineering, Construction and Architectural Management · doi:10.1108/09699980710731308 · Cited by 489
Olawale, Y. A., & Sun, M. (2010) · Construction Management and Economics · doi:10.1080/01446191003674519 · Cited by 478
Causes of Delay in Building Construction Projects in Egypt
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2008)134:11(831 · Cited by 463
Delays and cost increases in the construction of private residential projects in Kuwait
Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005) · Construction Management and Economics · doi:10.1080/0144619042000326710 · Cited by 456
Construction Delays and Their Causative Factors in Nigeria
Aibinu, A. A., & Odeyinka, H. A. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:7(667 · Cited by 348
Causes of delays in Saudi Arabian public sector construction projects
Al‐Kharashi, A., & Skitmore, M. (2009) · Construction Management and Economics · doi:10.1080/01446190802541457 · Cited by 327
Problems causing delays in major construction projects in Thailand
Toor, S.-U.-R., & Ogunlana, S. (2008) · Construction Management and Economics · doi:10.1080/01446190801905406 · Cited by 307
Delays and cost overruns in the construction projects in the Gaza Strip
Enshassi, A., Al‐Najjar, J., & Kumaraswamy, M. (2009) · Journal of Financial Management of Property and Construction · doi:10.1108/13664380910977592 · Cited by 278
Causes of delays on construction projects: a comprehensive list
Durdyev, S., & Hosseini, M. R. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-09-2018-0178 · Cited by 245
Delays in Building Construction Projects in Ghana
Fugar, F. D., & Agyakwah-Baah, A. B. (1970) · Construction Economics and Building · doi:10.5130/ajceb.v10i1-2.1592 · Cited by 211
“Financial difficulties have also been identified as the first major factor causing delay in construction projects in Malaysia (Alaghbari et al. 2007, Assaf et al. 1995).”
BackgroundMethodInfluentialRanking of delay factors in construction projects after Egyptian revolution
Aziz, R. F. (2013) · Alexandria Engineering Journal · doi:10.1016/j.aej.2013.03.002 · Cited by 209
Compressing construction durations: lessons learned from Hong Kong building projects
W.M. Chan, D., & M. Kumaraswamy, M. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00032-6 · Cited by 209
An evaluation of construction time performance in the building industry
Chan, D. W. M., & Kumaraswamy, M. M. (1996) · Building and Environment · doi:10.1016/0360-1323(96)00031-5 · Cited by 205
Delays in Building Construction Projects in Ghana
Fugar, F. D., & Agyakwah-Baah, A. B. (2010) · Australasian Journal of Construction Economics and Building · doi:10.5130/ajceb.v10i1/2.1592 · Cited by 203
Causes of delays in the construction industry in Lebanon
Mezher, T. M., & Tawil, W. (1998) · Engineering Construction and Architectural Management · doi:10.1046/j.1365-232x.1998.00049.x · Cited by 201
Root-Cause Analysis of Construction-Cost Overruns
Rosenfeld, Y. (2014) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000789 · Cited by 187
Causes of delay in the global construction industry: a meta analytical review
Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1716132 · Cited by 173
Applied artificial intelligence for predicting construction projects delay
Egwim, C. N., Alaka, H., Toriola-Coker, L. O., Balogun, H., & Sunmola, F. (2021) · Machine Learning with Applications · doi:10.1016/j.mlwa.2021.100166 · Cited by 125
Metadata
- Authors
- Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M.
- Venue
- Journal of Management in Engineering
- Published
- 1995-03
- Volume
- 11
- Issue
- 2
- Pages
- 45-50
- ISSN
- 0742-597X (ISSN-L)
- 1943-5479
- DOI
- 10.1061/(asce)0742-597x(1995)11:2(45
- OpenAlex
- W2127081806
- Cited by
- 544
- References
- 2
- FWCI
- 9.50
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.