Problems causing delays in major construction projects in Thailand
Abstract
Delays are frequent and recurring in construction projects in developing countries. Although the principal reasons for construction delays are comparable across developing countries, several factors pertaining to local industry, socio‐economic and cultural issues and project characteristics also contribute to construction delays. Questionnaire surveys and interviews were conducted on a major construction project in Thailand to explore the most significant problems causing construction delays. Factors related to designers, contractors and consultants were rated among the top problems. Issues such as lack of resources, poor contractor management, shortage of labour, design delays, planning and scheduling deficiencies, changed orders and contractors' financial difficulties were also highlighted during the interviews. Notably, problems such as ‘multicultural and multilingual environment causing ineffective communication’, ‘large number of participants of project’ and ‘involvement of several foreign designers and contractors’ were rated among the bottom 10 problems in the 75‐item problem inventory. These findings can be helpful for project managers to mitigate the construction delays in Thailand. In order to effectively overcome the construction delays in developing countries, suggestions are made for fundamental and large‐scale reforms in procurement systems, value chain management and stakeholders' management.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
(1984) · Cited by 81,983
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Research methods for construction
Fellowa, R., & Liu, A. M. M. (2003) · Cited by 1,448
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
The effects of construction delays on project delivery in Nigerian construction industry
Aibinu, A. A., & Jagboro, G. O. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00028-5 · Cited by 597
Significant factors causing delay in the UAE construction industry
Faridi, A. S., & El‐Sayegh, S. M. (2006) · Construction Management and Economics · doi:10.1080/01446190600827033 · Cited by 551
Causes of Delay in Large Building Construction Projects
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:2(45 · Cited by 544
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Delays and cost increases in the construction of private residential projects in Kuwait
Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005) · Construction Management and Economics · doi:10.1080/0144619042000326710 · Cited by 456
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Self-citationProblems in managing internal development projects in multi-project environments
Elonen, S., & Artto, K. A. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00097-2 · Cited by 374
Large construction projects in developing countries: a case study from Vietnam
Long, N. D., Ogunlana, S. O., Quang, T., & Lam, K. C. (2004) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.03.004 · Cited by 362
Self-citationEnvironmental factors and work performance of project managers in the construction industry
Pheng, L. S., & Chuan, Q. T. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.06.001 · Cited by 306
Delay Mitigation in the Malaysian Construction Industry
Abdul‐Rahman, H., Berawi, M. A., Berawi, A. R. B., Mohamed, O., Othman, M., & Yahya, I. A. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:2(125 · Cited by 256
Contributors to construction delays
Kumaraswamy, M. M., & Chan, D. W. M. (1998) · Construction Management and Economics · doi:10.1080/014461998372556 · Cited by 239
Causes of High Costs of Construction in Nigeria
Okpala, D. C., & Aniekwu, A. N. (1988) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1988)114:2(233 · Cited by 234
Jefferies, M. C., Gameson, R., & Rowlinson, S. (2002) · Engineering Construction & Architectural Management · doi:10.1108/eb021230 · Cited by 229
Causes of delays in the construction industry in Lebanon
Mezher, T. M., & Tawil, W. (1998) · Engineering Construction and Architectural Management · doi:10.1046/j.1365-232x.1998.00049.x · Cited by 201
Reasons for delays in public projects in Turkey
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · Construction Management and Economics · doi:10.1080/01446198500000013 · Cited by 198
Raftery, J., Pasadilla, B., Chiang, Y. H., Hui, E. C. M., & Tang, B.-S. (1998) · Construction Management and Economics · doi:10.1080/014461998372024 · Cited by 171
Causes of Delay in the Construction Industry
Baldwin, J. R., Manthei, J. M., Rothbart, H. A., & Harris, R. B. (1971) · Journal of the Construction Division · doi:10.1061/jcceaz.0000305 · Cited by 118
Reasons for overrun in public sector construction projects in Nigeria
Dlakwa, M. M., & Culpin, M. F. (1990) · International Journal of Project Management · doi:10.1016/0263-7863(90)90032-7 · Cited by 109
Delays on Large Construction Projects
Sullivan, A., & Harris, F. (1986) · International Journal of Operations & Production Management · doi:10.1108/eb054752 · Cited by 57
Developing a theory of construction problem solving
Li, H., & Love, P. E. D. (1998) · Construction Management and Economics · doi:10.1080/014461998372015 · Cited by 42
Cited by
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Critical Management Practices Influencing On-Site Waste Minimization in Construction Projects
Ajayi, S. O., Oyedele, L. O., Bilal, M., Akinade, O. O., Alaka, H. A., & Owolabi, H. A. (2017) · Waste Management · doi:10.1016/j.wasman.2016.10.040 · Cited by 200
Park, Y., & Papadopoulou, T. C. (2012) · Built Environment Project and Asset Management · doi:10.1108/20441241211280873 · Cited by 91
Construction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Metadata
- Authors
- Toor, S.-U.-R., & Ogunlana, S.
- Venue
- Construction Management and Economics
- Publisher
- Informa UK Limited
- Published
- 2008
- Volume
- 26
- Issue
- 4
- Pages
- 395-408
- ISSN
- 0144-6193 (ISSN-L)
- OpenAlex
- W2005215444
- Cited by
- 307
- References
- 28
- FWCI
- 5.64
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.