Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
The DOI matches its Crossref record; 6 of the 6 references it cites were found in a registry or an index.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Productivity improvement in construction
Oglesby, C. H., Parker, H. W., & Howell, G. A. (1988) · Medical Entomology and Zoology · Cited by 510
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 390
Causes of High Costs of Construction in Nigeria
Okpala, D. C., & Aniekwu, A. N. (1988) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1988)114:2(233 · Cited by 234
Cost overruns in public projects
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · International Journal of Project Management · doi:10.1016/0263-7863(85)90053-5 · Cited by 121
Reasons for overrun in public sector construction projects in Nigeria
Dlakwa, M. M., & Culpin, M. F. (1990) · International Journal of Project Management · doi:10.1016/0263-7863(90)90032-7 · Cited by 109
Cited by
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
Le-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-008-0367-7 · Cited by 560
Olawale, Y. A., & Sun, M. (2010) · Construction Management and Economics · doi:10.1080/01446191003674519 · Cited by 478
“…of view as delays in design information, long waiting time for approval of drawings, poor site management and supervision, mistakes and discrepancies in design documents, etc. Similar survey studies were reported by Frimpong et al (2003) in Ghana and by Assaf and Al-Hejji (2006) in Sandi Arabia.”
BackgroundResultUgwu, O. O., & Haupt, T. C. (2007) · Building and Environment · doi:10.1016/j.buildenv.2005.10.018 · Cited by 434
Analysis of cost and schedule performance of international development projects
Ahsan, K., & Gunawan, I. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.03.005 · Cited by 375
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000391 · Cited by 365
Taxonomy for change causes and effects in construction projects
Sun, M., & Meng, X. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.10.005 · Cited by 331
Doloi, H. (2013) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000621 · Cited by 325
Problems causing delays in major construction projects in Thailand
Toor, S.-U.-R., & Ogunlana, S. (2008) · Construction Management and Economics · doi:10.1080/01446190801905406 · Cited by 307
Delays and cost overruns in the construction projects in the Gaza Strip
Enshassi, A., Al‐Najjar, J., & Kumaraswamy, M. (2009) · Journal of Financial Management of Property and Construction · doi:10.1108/13664380910977592 · Cited by 278
Impact of integration management on construction project management performance
Demirkesen, S., & Ozorhon, B. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.09.008 · Cited by 259
Causes of delays on construction projects: a comprehensive list
Durdyev, S., & Hosseini, M. R. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-09-2018-0178 · Cited by 245
CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY
Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012) · Journal of Civil Engineering and Management · doi:10.3846/13923730.2012.698913 · Cited by 234
Delays in Building Construction Projects in Ghana
Fugar, F. D., & Agyakwah-Baah, A. B. (1970) · Construction Economics and Building · doi:10.5130/ajceb.v10i1-2.1592 · Cited by 211
“The high temperatures and high humidity ranging from 25 to 80% certainly affect the productivity of construction workers as a result of dullness of their senses, poor coordination and discomfort from body heat (Frimpong, Oluwoye, and Crawford, 2003).”
BackgroundCost overrun in the Malaysian construction industry projects: A deeper insight
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.04.004 · Cited by 210
“, 2013) and the significance of this, has attracted much research over recent decades (Arditi et al., 1985; Creedy, 2004; Dawood, 1998; Dlakwa and Culpin, 1990; Doloi, 2013; Frimpong et al., 2003; Kaming et al., 1997; Koushki et al., 2005; Mansfield et al., 1994).”
BackgroundRanking of delay factors in construction projects after Egyptian revolution
Aziz, R. F. (2013) · Alexandria Engineering Journal · doi:10.1016/j.aej.2013.03.002 · Cited by 209
Delays in Building Construction Projects in Ghana
Fugar, F. D., & Agyakwah-Baah, A. B. (2010) · Australasian Journal of Construction Economics and Building · doi:10.5130/ajceb.v10i1/2.1592 · Cited by 203
Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia
Rahman, I. A., Hameed Mem, A., & Abd. Karim, A. T. (2013) · Journal of Applied Sciences · doi:10.3923/jas.2013.286.293 · Cited by 193
Rowlinson, S., YunyanJia, A., Li, B., & ChuanjingJu, C. (2014) · Accident Analysis & Prevention · doi:10.1016/j.aap.2013.08.011 · Cited by 176
“The construction industry did not recognize it as a risk factor in accidents until quite recently (CSAO, 2000; Frimpong et al., 2003) although seasonal variation in construction accident rate with a peak appearing in summer months had been observed since at least the late 1970s (Helander, 1980).”
BackgroundTime and cost overruns in the UAE construction industry: a critical analysis
Johnson, R. M., & Babu, R. I. I. (2020) · International Journal of Construction Management · doi:10.1080/15623599.2018.1484864 · Cited by 173
Causes of delay in the global construction industry: a meta analytical review
Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1716132 · Cited by 173
An Analytical Network Process model for risks prioritisation in megaprojects
Boateng, P., Chen, Z., & Ogunlana, S. O. (2015) · International Journal of Project Management · doi:10.1016/j.ijproman.2015.08.007 · Cited by 172
Determining the Probability of Project Cost Overruns
Love, P. E. D., Wang, X., Sing, C.-P., & Tiong, R. L. K. (2013) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000575 · Cited by 169
Khodakarami, V., & Abdi, A. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.01.001 · Cited by 164
Causes of delay in residential construction projects in Cambodia
Durdyev, S., Omarov, M., & Ismail, S. (2017) · Cogent Engineering · doi:10.1080/23311916.2017.1291117 · Cited by 158
“This outcome substantiates the findings of Fugar and Agyakwah-Baah (2010), who ranked the aforementioned factors as one of the most influencing causes of construction project delay in Ghana.”
ResultPark, Y., & Papadopoulou, T. C. (2012) · Built Environment Project and Asset Management · doi:10.1108/20441241211280873 · Cited by 91
Kwon, H., & Kang, C. W. (2019) · Project Management Journal · doi:10.1177/8756972818810963 · Cited by 50
“The main causes of the delays and cost overruns were financial difficulties, poor resource management, and unexpected natural events (Frimpong et al., 2003).”
BackgroundConstruction delays in privately funded large building projects in Bangladesh
Islam, M. S., & Suhariadi, B. T. (2018) · Asian Journal of Civil Engineering · doi:10.1007/s42107-018-0034-3 · Cited by 44
Tembo-Silungwe, C. K., & Khatleli, N. (2017) · Acta Structilia · doi:10.18820/24150487/as24i2.1 · Cited by 3
Metadata
- Authors
- Frimpong, Y., Oluwoye, J., & Crawford, L.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2003-07
- Volume
- 21
- Issue
- 5
- Pages
- 321-326
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2049579974
- Cited by
- 796
- References
- 6
- FWCI
- 4.83
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.